Carson Street Ramps on SR 279

Location: Pittsburgh, PA
Owner: Penn DOT
General Contractor: Brayman Construction Corporation
Value: $4,800,000
Date Complete: 1997

 


Scope of Project:

Brayman completed the ramps for SR279 to the Fort Pitt Tunnels during the construction season of 1997. Since the ramps were located at one of the main arteries leading into Pittsburgh, heavy traffic was a tremendous challenge. Another challenge was the stringent time table as Ramp A had to be open in 137 calendar days and Ramp B had to be completed in only 90 days.

 

Download Printable PDF File of this project

Back to Bridge Project List

 

 

 

 

 

 

 

 

 

 

 

 
 