SR 119 - Port Marion Bridge

Location: Port Marion, PA
Owner: Penn DOT
General Contractor: Brayman Construction Corporation
Value: $6,700,000
Date Complete: August 1999

 


Scope of Project:

The Point Marion Bridge Project consisted of the construction of a 3-span steel girder bridge over the Cheat River and the demolition of an existing 3-span steel truss bridge. Brayman’s marine work included the construction of two 41’6” by 37’9” coffer dams, temporary shoring, steel beam piling, and realignment of the new bridge.

 