Scope of Project:
Brayman Construction was selected to perform dam modifications to the Lake Hamilton Dam consisting of the drilling and installation of 13 high capacity dam anchors. Working on the narrow stem section of the dam (6-feet wide), Brayman was able to successfully drill, watertightness test, consolidation grout, redrill, install and tension test each rock anchor. At three locations a permanent load cell was installed for future monitoring. |